Tuesday, September 11, 2012

There's a hole in the wall!

We got the go-ahead to proceed with taking out the old windows and part of the exterior wall in what is now the Traveling Exhibit space:

Hole in exterior wall of new Traveling Exhibit space.

This hole will be filled with a door and windows that will allow us to access the area behind Doc Knight's copper T. rex statue, which will be turned into a "T. rex Patio" space! For now it will be "bare bones" (so to speak) patio, with just pavers on gravel, but we hope to do an all-out landscaping project involving the patio area, the front of the Geological Survey building next door, and the area in front of the museum in the next few years as funds are raised. We've been working with a landscape designer who has drawn up plans for a very cool outside space with exhibits on the ancient rocks of Wyoming and geologic time, as well as an informal outside "classroom" area where we can work with schoolkids and other visitors on special projects and programs.

Other things going on:

The floor in the main exhibit space has been finished! The asbestos tiles were removed back in May, and now the old mastic was ground off and the concrete was polished and densified. So, we now have a gorgeous polished concrete floor that will never need waxing or finishing of any kind!  It's very nice:
New polished concrete floor (green center is artifact of camera)

This will be the floor surface around the center island, and also in the prep lab. The Traveling Exhibit space, the entire upstairs balcony, and each of the alcove spaces will have carpet squares:

New carpet for the alcoves, upstairs, and Traveling Exhibit


And, the electrical panels are being put in!

Voltech Electric putting in the new panels!

These are brand-new panels that will control all the electrical thingies in the whole museum. The lighting will be controlled by a separate panel, and we will no longer turn the lights off and on by flipping the breaker switches like we used to!

So, check back soon as things are starting to happen fast and furious around here!!

Wednesday, August 22, 2012





Alrighty, things are slowly moving forward!!

In the main exhibit space, the Boxosaurus is coming down so that the concrete floor it is attached to can be densified and polished. (Sorry about the grainy picture, but the light is very low in the space since there are no actual lights yet...we just have construction lights hanging off the balcony.)

We've gotten so used to having a giant box in the middle of the museum, it's gonna be s shock to see a giant dinosaur or two there instead...

The Stegosaurus cast has been moved downstairs and now hangs on the new wall at the north end. The entrance to the glowing rocks room is now on the right side of the stego.


We've gotten the new fossil prep lab walls and ceiling painted:


And the new Traveling Exhibit space is painted also:


More pictures soon!






Monday, August 6, 2012

August 6, 2012

Things are progressing again in the museum renovations! We've got electricians and plumbers and painters, oh my!

The electrical stuff is getting done, but there's not much to see as it's mostly in the walls and ceiling. Painting started this afternoon, and I'll post photos once that is done. They will be starting with the ceiling and then moving on to all the walls upstairs and down. Once the ceiling is painted, Marshall Contracting will start taking down the Boxosaurus so that the floor it is attached to can get done.

The walls in the back room are getting drywalled and will be ready for painting later today:

New wall separating newTraveling Exhibit space from prep lab, with 
office in the background.


They've also built the new wall that extends out from the end of the fluorescent minerals room, and closed off the minerals room, too. The future entrance to the glowing rocks room will be on the far right. The stegosaurus cast from upstairs will go on this wall, once the electrical box is moved to the back room!

Closing off the glowing rocks door


We'll have more new pics once the painting is done in a couple of days!!

Monday, July 9, 2012

July 9, 2012

Well, things are progressing in the museum slowly as we wait for the bidding process to be done and the electrical, plumbing, etc. subcontractors to come on board. We have been working on more ideas for the exhibits, and trying to plan for the flurry of activity that will come once the upstairs is done and we can move the exhibits that are stored in a classroom back into the museum in time for classes to start!

The new wall in the back room is in the process of being framed in to separate the future prep lab from the future traveling exhibit space:

Front of viewable prep lab, with windows and door in the middle.


View from inside future prep lab.

The large boxes you see are covering open jackets of dinosaur bones that are partially finished and were just to fragile and too big to move out of the back room. So, our thoughtful construction folks made mini-boxosauruses to protect these specimens during construction! 

The future Cretaceous exhibit space is coming together, wall studs across the back where a large mural
will be placed:
      


I will have more updates soon!!

Wednesday, June 13, 2012

June 13, 2012

Well, things are slowing down in the renovations. The demolition part of things is pretty much done, and the lights are down in the main exhibit space:

The fiberglass models of T. rex and Allosaurus have now gone to a new home at the Tate Museum in Casper, since we just won't have room for them in the new museum design. So, J-P Cavigelli from the Tate came down with a student and picked up the models to take them to their new home.


They fit just fine in the Tate's Suburban, which was a little disappointing because we didn't get to strap them to the roof and drive down the highway...

One exciting thing that's been finished is the floor in what will soon be our new prep lab. 


The floor used to be covered with the old asbestos tiles. Once those were removed, the mastic was ground off and the original cement floor was exposed. Then the concrete was densified, creating a glossy surface that is very durable and won't need any polishing. Very cool!!




Friday, June 1, 2012

Friday, June 1, 2012 (again)

Holy moly, look what happened this morning!!



This is the spot where the "What is a fossil" exhibit used to live, and it is now going to be the entrance into the traveling exhibit space. A wall will be built at the edge of the new hole to separate the traveling exhibit space from the new prep lab.

Yeehaw!!!


Friday, June 1, 2012

Lots to report this week!

The asbestos abatement of the back room floor tiles started on Tuesday afternoon, and was done by Thursday afternoon:

The next step in this room is to grind the floor down to the concrete and seal it. Then we will move the things that will stay in the new prep lab back in there before the wall is built to separate the future prep lab and traveling exhibit spaces. 

Back in the main exhibit space:

In preparation for being completely removed and re-built to code, the railing on the staircase on the south end of the museum was taken off: 


and then the rest of the staircase was un-bolted and came apart fairly easily:


Cases are being removed to make several of the alcoves bigger:


The process of breaking through the cement-block wall to create the new opening between the main exhibit space and the future traveling exhibit area has started:


And the wall on the end of the fluorescent minerals room has also been partially removed:

This area will be part of a future mineral exhibit that looks like a mine, and the fluorescent minerals room will be entered from the side rather than from the front.


It's pretty dusty in there, but the demolition will be done soon and the process of re-building can start!